When Pamela reached out about the guest bathroom in her Pflugerville home, the room had barely changed since the house was built. The tub was worn, the wall surround was dated, and guests had started to notice. She wanted the space rebuilt around a new tub and fully tiled shower walls. Nothing flashy, just a clean room done correctly. It was exactly the kind of bathroom remodel Pflugerville TX homeowners call us about every week, so we documented the project from the first sheet of floor protection to the final coat of sealer. Here is how it went.

Key Takeaways

  • Pamela’s guest bathroom remodel was built around a new tub with a left side drain and roughly 90 square feet of white wall tile.
  • A full site protection package kept dust out of the rest of the house, with ram board, sticky nylon, plastic sheeting, and zipper walls.
  • The shower walls received three layers of protection: mold block with moisture resistant paper, waterproofing board, and a liquid membrane over every wall and the shampoo niche.
  • A bathroom remodel Pflugerville TX homeowners plan around a tub and tile shower generally runs between $8,000 and $15,000 depending on tile, plumbing changes, and room size.
  • We tie payments to milestones like demolition, waterproofing, and tile, so you pay as the work gets done.

The Scope of the Project

Every project we take on starts with a written estimate that spells out exactly what will happen and in what order. Pamela’s covered demolition, site protection, plumbing, waterproofing, tile, and fixtures. It is the same structure we use across our bathroom remodeling service, whether the project is a guest bath or a large primary suite. Here is what each stage looked like in her home.

Project DetailSpecification
LocationPflugerville, TX
ProjectGuest bathroom remodel for our client Pamela
ScopeNew tub with a left side drain and fully tiled shower walls
Wall tileRoughly 90 square feet of white tile with Schluter edge profiles
WaterproofingMold block paper, waterproofing board, and liquid membrane
FixturesNew shower head, handheld faucet, and shower curtain kit
Typical cost range$8,000 to $15,000 for this kind of project in the area
Working timelineAbout 2 to 3 weeks from demolition to final fixtures

Demolition and Haul Away

The old tub, the surround, and the existing finishes all came out, and we handled the full debris haul away ourselves. Nothing sat in the driveway waiting on a dumpster. We will be honest about this stage because not every contractor is. Demolition is loud and it makes dust. There is no quiet way to break tile off a wall. What a good crew can do is contain the mess, work in focused stretches, and move through it fast. That is what we did here, and the noisy part of the project was over within days.

Protecting the Rest of the House

Before a single hammer swung, the covering package went in. Ram board protected the floors along the work path. Sticky nylon held down coverage where regular sheeting slips. Moisture resistant paper and 6 mil plastic covered nearby surfaces, and zipper walls held up with tape and painter’s poles sealed the bathroom off from the rest of the home. Pamela lived her normal routine on the other side of that plastic for the entire project. This setup takes a few hours and it earns back every minute.

Plumbing Brought Up to Code

With the room open to the studs, the plumbing was prepared and adjusted to meet current code. The shower valve was relocated, and the hot and cold supply lines were moved to match the new layout. The new tub then went in with a left side drain to suit the room. Getting rough plumbing right at this stage is what keeps the rest of the project simple. It gets inspected, we photograph it, and it only disappears behind the wall once it is correct.

Tile, Grout, and Fixtures

Pamela chose a white wall tile herself, and we installed roughly 90 square feet of it across the shower walls. Schluter edge profiles finished the exposed edges, which gives every corner a crisp metal line instead of a row of raw tile cuts. All of it was grouted with mold resistant grout and sealed. For fixtures, she received a new shower head and a handheld faucet, plus a complete shower curtain kit so the bathroom was ready to use the day we wrapped up. Pamela wanted to keep her tub, but a tub to shower conversion follows these same stages if you would rather have a walk in shower. If you are picking fixtures for your own project, the EPA WaterSense program is worth a look. Certified shower heads use about 20 percent less water without feeling weak.

tub and tile shower with a shower curtain kit in a Pflugerville guest bathroom remodel

Why Shower Waterproofing Matters More Than the Tile

Here is something that surprises most homeowners: tile and grout are not waterproof. Water vapor passes through grout lines, and over the years even hairline gaps let moisture reach whatever sits behind the tile. Shower waterproofing is the work that decides whether your new bathroom lasts for decades or fails quietly in a few years, and it is completely invisible the day the project wraps up. That is exactly why we build it in layers and photograph every one of them before tile goes on.

The first layer in Pamela’s shower was mold block with moisture resistant paper, applied over the framing. Think of it as defense in depth. If moisture ever gets past everything above it, this layer shields the wood studs and gives mold nothing to feed on. Skip it and any future leak soaks straight into the framing, where it can rot structural lumber for years before anyone notices a smell or a stain.

Waterproofing board went on next. It replaces ordinary drywall inside the wet area with a rigid, water resistant surface that tile can bond to for the long haul. Plain drywall behind a shower is one of the most common failures we open up in older homes. It wicks water like a sponge, swells, and slowly releases the tile bond until whole sections crack loose along the grout lines.

The final layer was a liquid waterproofing membrane rolled across the entire shower wall area and the shampoo niche. Boards resist water, but the seams, screw heads, and corners between them do not. The membrane ties the whole assembly into one continuous barrier. The niche matters most here. A shampoo niche is a box cut into a wet wall, which makes it the most leak prone spot in the entire shower. When a niche fails, it is almost always because someone treated the membrane over it as optional.

None of this is guesswork. The Tile Council of North America publishes the standards professional tile installers follow, and layered shower waterproofing is how those standards get met on a real job site. When you compare bids, ask each contractor to walk you through their shower waterproofing stack in plain language. A contractor who cannot name the layers is telling you something important.

new shower head on white tile shower walls in a guest bathroom remodel Pflugerville TX

Bathroom Remodel Pflugerville TX: What a Guest Bath Costs

Pamela’s contract is her business, and we do not publish client pricing. What we can share is an honest market range. In the Pflugerville area, a guest bathroom remodel built around a new tub and fully tiled shower walls generally lands between $8,000 and $15,000. Tile selection moves that number more than most people expect, since material prices vary widely and intricate patterns add labor. Plumbing changes matter too, because relocating a valve or supply lines adds licensed trade work. Room size rounds out the big three. A tub to shower conversion usually lands in a similar range.

If you have been searching for bathroom renovation cost Pflugerville numbers and getting vague answers, ranges like this are the honest version. Any firm number requires someone to actually look at your bathroom. One thing we do on every project is tie the payment schedule to milestones rather than dates. A typical schedule releases a payment after demolition, another after waterproofing, and another once tile is complete. You always know what you are paying for because you can walk in and see it on the wall.

For a deeper look at pricing across project sizes, our guide to bathroom remodel cost in Austin breaks the numbers down. And if you are wondering about schedule, we covered how long a kitchen or bathroom remodel takes in a separate post.

Frequently Asked Questions

How long does a bathroom remodel take?

A guest bathroom remodel like this one, a tub and tile shower, takes about 2 to 3 weeks from demolition to final fixtures. Larger projects run longer, especially when the layout changes or custom materials have long lead times. Waterproofing cure times set part of the pace, and rushing them is how showers fail early.

How much will it cost to remodel a small bathroom?

Most small bathroom and guest bathroom remodels in the Pflugerville area run between $8,000 and $15,000. Tile choice, plumbing changes, and room size move the final number inside that range. We structure payments around milestones such as demolition, waterproofing, and tile, so you pay as each stage is completed.

Serving Pflugerville, Round Rock, and North Austin

Our crews are in this corner of the metro every week. We work throughout Pflugerville, from established neighborhoods near downtown out to Falcon Pointe, Blackhawk, and Avalon. We also serve Round Rock, Hutto, Wells Branch, and North Austin along the Interstate 35 corridor. Working close to home matters in remodeling. Crews arrive on time, material runs are short, and if something needs attention after completion, we are nearby to handle it. Pamela found us the way most of our Pflugerville clients do, through a neighbor who had already worked with us. Every bathroom remodel Pflugerville TX clients hire us for gets the same site protection and waterproofing standards you read about above, and the same goes for each bathroom remodel Round Rock TX homeowners bring us. If you are comparing bathroom remodeling Pflugerville companies, ask every one of them to explain their waterproofing before you compare prices.

Ready to Rebuild Your Guest Bathroom?

If your guest bath is overdue for the same treatment Pamela’s got, we would love to see it. BH Remodeling is a family owned, licensed and insured bathroom remodeling contractor Pflugerville homeowners have trusted since 2012, and every bathroom remodel Pflugerville TX project starts with a real conversation rather than a sales pitch. Reach out through our contact page for a free estimate. First We Listen. Then We Build.